Diversity Construction Group was awarded the contract to install a new oil/water separator at the New Milford Fire Station in July 2022. The $71,625 project includes the installation of a new trench drain system inside the fire station with an 8″ thick concrete slab slated to enclose it.

Other work required included the installation of new piping leading to the new precast concrete separator.

Construction work began in August and substantial completion was achieved in October 2022.

Client: Town of New Milford

Architect/Engineer:  New Milford Dept. of Public Works

Project Delivery: General Contractor